The company has established the enterprise goal of "survival by quality, reputation by quality, and development by quality. Strengthen the training of technical personnel, and constantly enrich the first-line technical force to ensure the normal operation of the quality assurance system.

Introduction of vacuum emulsifying machine operation steps


Release time:

2019-08-08

  vacuum emulsifying machineOperation process

1. Check whether each switch and valve is in the original position.

2. Check whether the rolling parts such as homogeneous part, mixing slurry and cylinder scraper are safe, reliable and firm.

3. Check whether the power supply voltage, appearance and instructions are normal.

4. Check whether there is water in the heating interlayer, and do not start the machine when the liquid level is lower than the heating rod.

5. Turn on the power switch and observe whether the appearance is normal.

6. Feeding is required during operation, and mixing is required for heating.

7. Only when there are enough materials in the pot can the homogenizer be started and mixed together. The mixing speed shall be adjusted upward from zero and adjusted to the required speed.

8. If any problem with the homogenizer is found during operation, the power supply should be turned off quickly and disassembled for maintenance. When opening the vacuum system, first open the vacuum control switch, and then open the vacuum pipeline valve. When closing, close the vacuum management valve first, then close the power supply. When the negative pressure is 0.05mpa to 0.06mpa, open the feed valve to absorb 70% of the water. After absorbing the oil, absorb 30% of the water. And often check whether the filter is complete, so as to avoid debris into the emulsifying pot, to ensure the normal operation of the homogenizer. The vacuum degree in the emulsifying pot should not be too high, generally kept between 0.05mpa and 0.06mpa, so as not to cause the water to boil.

9. The work buckle must be supervised by a special person, and the person will stop when leaving the plane.

10. Stop the machine and adjust the speed to zero first. Press the mix stop button again.

11. Turn off the power switch, check whether the water valve is closed, open the vacuum exhaust valve.

12. After discharging the semi-finished products, clean the residue in the pot with warm water to keep the pot clean.

13. The motor and the pump are lubricated and fastened to the parts that are easy to loosen.

14. Each shift must make records of equipment operation and routine maintenance.