Precautions for Installation and Commissioning of High Shear Homogeneous Emulsion Machine


Release time:

2019-05-14

1. the power supply, the power supply is consistent, and pay attention to the reliable grounding of the ground wire, turn on the main power switch, the power indicator light is on. (After the motor is wired or is not used for long-term re-start, it should be inching to test the rotation, and the rotation of the mixing frame is reversed from top to bottom. When debugging, it should be inching to test the rotation, and then let the homogenizer run when it is confirmed to be correct!) 2. correctly connect all pipes of the homogenizing pot (including each overflow port, drain port and sewage outlet). Before vacuuming the 3., be sure to check whether the pan is flat with the pan cover, whether the pan mouth and the material port cover are tightly covered and reliably sealed. Close the valve interface on the lid, and then open the vacuum valve on the lid

1. the power supply, the power supply is consistent, and pay attention to the reliable grounding of the ground wire, turn on the main power switch, the power indicator light is on. (After the motor is wired or is not used for long-term re-start, it should be inching to test the rotation, and the rotation of the mixing frame is reversed from top to bottom. When debugging, it should be inching to test the rotation, and then let the homogenizer run when it is confirmed to be correct!)
2. correctly connect all pipes of the homogenizing pot (including each overflow port, drain port and sewage outlet).
Before vacuuming the 3., be sure to check whether the pan is flat with the pan cover, whether the pan mouth and the material port cover are tightly covered and reliably sealed. Close the valve interface on the lid, then open the vacuum valve on the lid, then open the vacuum pump to vacuum, close the vacuum pump when the requirements are met, and close the vacuum valve at the same time. (See operation process flow chart for details)
4. homogenization cutting and scraper stirring: after feeding (water can be used instead during debugging), turn on the corresponding control switches to control the operation of homogenizer and scraper stirring respectively. Before the start of stirring, it should also be inched to check whether there is any abnormality in the stirring scraping wall, and if so, it should be eliminated immediately.
The 5. vacuum pump can only be started when the homogenizing pot is sealed. If there is a special need to open the atmosphere to start the pump, the operation can not be over 3 minutes.
6. vacuum pump is strictly prohibited without working fluid operation. Do not block the exhaust port when the pump is running.
7. regularly check the lubricating oil and grease in each component and bearing, and replace the lubricating oil and grease in time.
8. keep the homogenizer clean. Every time you want to stop using or replace materials, you should clean the part of the homogenizer in contact with the working fluid, especially the cutting wheel cutting sleeve of the head, the sliding bearing in the homogeneous shaft sleeve and the shaft sleeve. After cleaning and reassembling, the hand-turned impeller shall be free of jamming. After the two flanges of the pot body and the pot cover are relatively fixed, the inching homogenizer motor can turn correctly and start operation without other abnormalities.
9. cleaning of all pots is handled by the user as standard.